CO plant
Project: |
CO plant |
Client: |
Sazeh Consultants |
Owner: |
Fanavaran Petrochemical Company |
Location: |
Bandar Imam, Iran |
Cooperation With Other Companies: |
|
Services: |
Engineering Services
Procurement
Project management for engineering and procurement services |
The plan shall consist of the following process units/unit and all necessary ancillaries:
1- Feed gas preparation and desulphurization process unit (if necessary) consisting of:
- Feed gas preheating section
- Feed gas desulphurization section
- Reforming section
- Waste heat recovery/steam production section
2 - CO2 removal process unit consisting of:
- Absorption of CO2 section
- Regeneration of solvent solution section
- Final cooling section
3 - Purification process unit consisting of:
- CO purification (by cryogenics-compression) section
- Drying section
4 - Interconnection, tankage and other auxiliary facilities units of “unit”
As a whole, the plant shall produce 14000 MTPY final CO products based on 7920 hours per year. |